Dept. of Trans. PROGRESS Serial No. Contract No. 02-170-17-28 07-141004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 46% 67% 07-LA-110-23.7/29.9 Federal Project: ACNH-S110(7) Progress payment No. 07 Payment period ending: 06-20-02 L A SIGNAL P O BOX 3078 INDUSTRY CA 91744 Escrow No. 01852 Total Estimate This Estimate 1. Contract Itms Without Mobil. 591,838.75 74,915.12 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 261,274.67 0.00 4. Earned Subject to Retention 853,113.42 74,915.12 5. Mobilization 157,996.00 7,899.80 6. Total Work Completed 749,834.75 7. Deductions -17,600.00 0.00 8. a.Contract Retentions -42,655.67 -3,745.75 b. Unsatisfactory Prog. -3,745.76 -3,745.76 c. Reduction after 95% Comp. 9. Total pay to Contractor 947,107.99 75,323.41 10. Reduction Amt to Escrow 11. Payment to Escrow 42,650.00 12. Net Pymt. this Estimate 75,323.41