Dept. of Trans. PROGRESS Serial No. Contract No. 02-206-11-46 07-141004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 77% 07-LA-110-23.7/29.9 Federal Project: ACNH-S110(7) Progress payment No. 08 Payment period ending: 07-20-02 L A SIGNAL P O BOX 3078 INDUSTRY CA 91744 Escrow No. 01852 Total Estimate This Estimate 1. Contract Itms Without Mobil. 721,446.55 129,607.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 217,728.89 -43,545.78 4. Earned Subject to Retention 939,175.44 86,062.02 5. Mobilization 157,996.00 0.00 6. Total Work Completed 879,442.55 7. Deductions -9,600.00 8,000.00 8. a.Contract Retentions -46,958.77 -4,303.10 b. Unsatisfactory Prog. -8,048.86 -4,303.10 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,032,563.81 85,455.82 10. Reduction Amt to Escrow 11. Payment to Escrow 46,950.00 12. Net Pymt. this Estimate 85,455.82