Dept. of Trans. PROGRESS Serial No. Contract No. 07-234-07-44 07-1661A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 50% 07-LA-1-28.7/29.6 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-07 LOS ANGELES ENGINEERING INC 633 N. BARRANCA AVE COVINA, CA 91723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 516,878.40 269,350.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 516,878.40 269,350.00 5. Mobilization 230,250.00 76,750.00 6. Total Work Completed 747,128.40 7. Deductions 8. a.Contract Retentions -51,687.84 -26,935.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 695,440.56 319,165.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 319,165.00