Dept. of Trans. PROGRESS Serial No. Contract No. 11-081-10-06 07-168004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 47% 07-LA-5-R44.2/R46.0 Federal Project: CMLN-6207(46) Progress payment No. 35 Payment period ending: 03-20-11 M C M SECURITY PAVING J V P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 70,236,996.08 770,993.74 2.a. Extra Work 7,638,835.87 14,554.08 b. Adjustment Comp. 1,121,250.41 0.00 3. Materials on Hand 2,316,985.67 -108,726.33 4. Earned Subject to Retention 81,314,068.03 676,821.49 5. Mobilization 10,307,938.00 0.00 6. Total Work Completed 89,305,020.36 7. Deductions -7,500.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 91,614,506.03 676,821.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 676,821.49