Dept. of Trans. PROGRESS Serial No. Contract No. 12-170-14-12 07-168004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 69% 07-LA-5-R44.2/R46.0 Federal Project: CMLN-6207(46) Progress payment No. 52 Payment period ending: 06-20-12 M C M SECURITY PAVING J V P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 96,902,250.57 2,340,982.20 2.a. Extra Work 9,066,083.97 29,015.67 b. Adjustment Comp. 2,851,834.63 5,722.40 3. Materials on Hand 276,908.57 -12,560.64 4. Earned Subject to Retention 109,097,077.74 2,363,159.63 5. Mobilization 10,307,938.00 0.00 6. Total Work Completed 119,128,107.17 7. Deductions -25,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 119,380,015.74 2,358,159.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,358,159.63