Dept. of Trans. PROGRESS Serial No. Contract No. 05-145-09-22 07-1693A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 23% 07-LA-90-R1.0/R1.8 Federal Project: NONE Progress payment No. 02 Payment period ending: 05-20-05 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02194 Total Estimate This Estimate 1. Contract Itms Without Mobil. 334,802.00 196,520.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 44,606.96 44,606.96 4. Earned Subject to Retention 379,408.96 241,126.96 5. Mobilization 165,000.00 55,000.00 6. Total Work Completed 499,802.00 7. Deductions 8. a.Contract Retentions -37,940.90 -24,112.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 506,468.06 272,014.26 10. Reduction Amt to Escrow 11. Payment to Escrow 37,940.00 12. Net Pymt. this Estimate 272,014.26