Dept. of Trans. PROGRESS Serial No. Contract No. 05-172-12-51 07-1693A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 35% 07-LA-90-R1.0/R1.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-20-05 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 02194 Total Estimate This Estimate 1. Contract Itms Without Mobil. 525,067.00 190,265.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -44,606.96 4. Earned Subject to Retention 525,067.00 145,658.04 5. Mobilization 165,000.00 0.00 6. Total Work Completed 690,067.00 7. Deductions 8. a.Contract Retentions -52,506.70 -14,565.80 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 637,560.30 131,092.24 10. Reduction Amt to Escrow 11. Payment to Escrow 52,500.00 12. Net Pymt. this Estimate 131,092.24