Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-140-11-46 07-1693A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-90-R1.0/R1.8 Federal Project: NONE Progress payment No. 26 Payment period ending: 03-10-08 D W POWELL CONSTRUCTION INC 8555 BANANA AVE FONTANA CA 92335-3019 Escrow No. 02194 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,635,872.73 24,275.50 2.a. Extra Work 280,528.44 11,491.54 b. Adjustment Comp. 1,773.98 -11,749.53 3. Materials on Hand 4. Earned Subject to Retention 2,918,175.15 24,017.51 5. Mobilization 220,000.00 0.00 6. Total Work Completed 3,138,175.15 7. Deductions -5,000.00 16,000.00 8. a.Contract Retentions -139,771.83 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 139,771.83 0.00 9. Total pay to Contractor 3,133,175.15 40,017.51 10. Reduction Amt to Escrow -139,670.00 0.00 11. Payment to Escrow 139,670.00 12. Net Pymt. this Estimate 40,017.51