Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 02-275-07-40 07-1760U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 29% 07-LA-5-R52.7/53.7 Federal Project: ACNH-005-3(26) I-005-3(26) ACNH-005-3(26) Progress payment No. 10 Payment period ending: 09-20-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01890 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,532,109.57 23,360.47 2.a. Extra Work 4,152.33 0.00 b. Adjustment Comp. 3. Materials on Hand 2,604,080.42 65,699.30 4. Earned Subject to Retention 6,140,342.32 89,059.77 5. Mobilization 2,838,956.25 0.00 6. Total Work Completed 6,375,218.15 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -558,860.52 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,400,438.05 89,059.77 10. Reduction Amt to Escrow 11. Payment to Escrow 558,860.00 12. Net Pymt. this Estimate 89,059.77