Dept. of Trans. PROGRESS Serial No. Contract No. 03-204-13-26 07-1760U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 46% 45% 07-LA-5-R52.7/53.7 Federal Project: ACNH-005-3(26) I-005-3(26) ACNH-005-3(26) Progress payment No. 20 Payment period ending: 07-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01890 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,389,891.65 842,331.82 2.a. Extra Work 352,752.39 64,265.80 b. Adjustment Comp. 810,943.83 774,495.83 3. Materials on Hand 537,483.03 14,416.73 4. Earned Subject to Retention 12,091,070.90 1,695,510.18 5. Mobilization 2,838,956.25 0.00 6. Total Work Completed 14,392,544.12 7. Deductions -35,250.00 -10,000.00 8. a.Contract Retentions -604,553.55 -45,693.03 b. Unsatisfactory Prog. 0.00 46,201.29 c. Reduction after 95% Comp. 9. Total pay to Contractor 14,290,223.60 1,686,018.44 10. Reduction Amt to Escrow 11. Payment to Escrow 604,550.00 12. Net Pymt. this Estimate 1,686,018.44