Dept. of Trans. PROGRESS Serial No. Contract No. 03-267-15-09 07-1760U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 50% 07-LA-5-R52.7/53.7 Federal Project: ACNH-005-3(26) I-005-3(26) ACNH-005-3(26) Progress payment No. 22 Payment period ending: 09-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01890 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,681,687.98 618,502.56 2.a. Extra Work 418,647.51 33,681.77 b. Adjustment Comp. 821,391.83 0.00 3. Materials on Hand 690,537.08 53,546.38 4. Earned Subject to Retention 13,612,264.40 705,730.71 5. Mobilization 2,838,956.25 0.00 6. Total Work Completed 15,760,683.57 7. Deductions -25,250.00 -10,000.00 8. a.Contract Retentions -680,613.22 -35,286.54 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,745,357.43 660,444.17 10. Reduction Amt to Escrow 11. Payment to Escrow 680,610.00 12. Net Pymt. this Estimate 660,444.17