Dept. of Trans. PROGRESS Serial No. Contract No. 03-330-10-32 07-1760U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 55% 07-LA-5-R52.7/53.7 Federal Project: ACNH-005-3(26) I-005-3(26) ACNH-005-3(26) Progress payment No. 25 Payment period ending: 11-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01890 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,636,897.89 1,469,465.99 2.a. Extra Work 505,369.70 35,593.05 b. Adjustment Comp. 1,826,233.33 0.00 3. Materials on Hand 1,017,602.64 198,521.48 4. Earned Subject to Retention 16,986,103.56 1,703,580.52 5. Mobilization 2,988,375.00 149,418.75 6. Total Work Completed 18,956,875.92 7. Deductions -25,250.00 -10,000.00 8. a.Contract Retentions -849,305.18 -85,179.03 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,099,923.38 1,757,820.24 10. Reduction Amt to Escrow 11. Payment to Escrow 849,300.00 12. Net Pymt. this Estimate 1,757,820.24