Dept. of Trans. PROGRESS Serial No. Contract No. 04-238-12-43 07-1760U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 79% 07-LA-5-R52.7/53.7 Federal Project: ACNH-005-3(26) I-005-3(26) ACNH-005-3(26) Progress payment No. 35 Payment period ending: 08-20-04 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01890 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,224,009.49 724,360.53 2.a. Extra Work 887,901.17 56,671.60 b. Adjustment Comp. 1,869,739.73 0.00 3. Materials on Hand 130,359.57 130,359.57 4. Earned Subject to Retention 24,112,009.96 911,391.70 5. Mobilization 2,988,375.00 0.00 6. Total Work Completed 26,970,025.39 7. Deductions -75,250.00 0.00 8. a.Contract Retentions -1,205,600.50 -45,569.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,819,534.46 865,822.11 10. Reduction Amt to Escrow 11. Payment to Escrow 1,205,600.00 12. Net Pymt. this Estimate 865,822.11