Dept. of Trans. PROGRESS Serial No. Contract No. 04-023-16-42 07-178704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 48% 07-LA-134-5.6/ .0 Federal Project: ACNH-P134(30) Progress payment No. 05 Payment period ending: 01-20-04 O DONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 02129 Total Estimate This Estimate 1. Contract Itms Without Mobil. 488,517.17 44,368.97 2.a. Extra Work 23,559.79 1,321.80 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 512,076.96 45,690.77 5. Mobilization 210,000.00 0.00 6. Total Work Completed 722,076.96 7. Deductions -15,699.74 -4,436.89 8. a.Contract Retentions -51,207.70 -4,569.08 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 655,169.52 36,684.80 10. Reduction Amt to Escrow 11. Payment to Escrow 51,200.00 12. Net Pymt. this Estimate 36,684.80