Dept. of Trans. PROGRESS Serial No. Contract No. 04-205-10-40 07-178704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 93% 07-LA-134-5.6/ .0 Federal Project: ACNH-P134(30) Progress payment No. 11 Payment period ending: 07-20-04 O DONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 02129 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,185,245.49 47,474.80 2.a. Extra Work 43,836.12 4,936.14 b. Adjustment Comp. 3. Materials on Hand 50,121.10 0.00 4. Earned Subject to Retention 1,279,202.71 52,410.94 5. Mobilization 266,000.00 0.00 6. Total Work Completed 1,495,081.61 7. Deductions -26,657.34 0.00 8. a.Contract Retentions -63,960.14 -2,620.55 b. Unsatisfactory Prog. 0.00 20,268.51 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,454,585.23 70,058.90 10. Reduction Amt to Escrow 11. Payment to Escrow 63,960.00 12. Net Pymt. this Estimate 70,058.90