Dept. of Trans. PROGRESS Serial No. Contract No. 04-057-11-09 07-181604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 59% 07-LA-91-R14.0/R20.7 Federal Project: ACNH-P091(112) Progress payment No. 18 Payment period ending: 02-20-04 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE STREET BALDWIN PARK CA 917061747 Escrow No. 01994 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,087,791.03 511,683.60 2.a. Extra Work 558,066.33 41,528.42 b. Adjustment Comp. 3. Materials on Hand 140,622.41 64,042.42 4. Earned Subject to Retention 8,786,479.77 617,254.44 5. Mobilization 1,691,000.00 0.00 6. Total Work Completed 10,336,857.36 7. Deductions 8. a.Contract Retentions -439,323.99 -30,862.72 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,038,155.78 586,391.72 10. Reduction Amt to Escrow 11. Payment to Escrow 439,320.00 12. Net Pymt. this Estimate 586,391.72