Dept. of Trans. FINAL Serial No. Contract No. 08-302-13-27 07-181804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-1-40.8/ .0 Federal Project: ACST-35H4(4) P-35H4(4) Progress payment No. 27 Payment period ending: 12-29-03 PKB CONSTRUCTION INC P O BOX 661717 ARCADIA CA 910661717 Escrow No. 01914 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,651,268.93 0.00 2.a. Extra Work 226,604.37 0.00 b. Adjustment Comp. 606,953.35 353,136.14 3. Materials on Hand 4. Earned Subject to Retention 3,484,826.65 353,136.14 5. Mobilization 550,851.00 0.00 6. Total Work Completed 4,035,677.65 7. Deductions 8. a.Contract Retentions -148,582.10 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 148,582.10 0.00 9. Total pay to Contractor 4,035,677.65 353,136.14 10. Reduction Amt to Escrow -148,580.00 0.00 11. Payment to Escrow 148,580.00 12. Net Pymt. this Estimate 353,136.14