Dept. of Trans. PROGRESS Serial No. Contract No. 10-113-07-00 07-182704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-134-5.9/8.6 Federal Project: NONE Progress payment No. 29 Payment period ending: 04-20-10 BELAIRE WEST LANDSCAPE INC P O BOX 6270 BUENA PARK CA 90622 Escrow No. 02341 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,724,325.70 11,200.00 2.a. Extra Work 145,313.30 625.52 b. Adjustment Comp. -18,630.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,851,009.00 11,825.52 5. Mobilization 250,000.00 0.00 6. Total Work Completed 2,101,009.00 7. Deductions -41,332.30 0.00 8. a.Contract Retentions -92,550.45 -591.28 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,967,126.25 11,234.24 10. Reduction Amt to Escrow 11. Payment to Escrow 92,550.00 12. Net Pymt. this Estimate 11,234.24