Dept. of Trans. PROGRESS Serial No. Contract No. 09-056-08-42 07-183114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 23% 07-LA-710-9.4/18.4 Federal Project: ACNH-710(786) Progress payment No. 20 Payment period ending: 02-20-09 ATKINSON CONTRACTORS LP 27422 PORTOLA PARKWAY STE 250 FOOTHILL RANCH CA 92610 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 50,376,684.13 4,310,767.20 2.a. Extra Work 815,164.43 33,766.21 b. Adjustment Comp. 282,575.60 -59,180.28 3. Materials on Hand 489,359.90 -29,086.76 4. Earned Subject to Retention 51,963,784.06 4,256,266.37 5. Mobilization 13,300,000.00 0.00 6. Total Work Completed 64,774,424.16 7. Deductions -345,400.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 64,918,384.06 4,256,266.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,256,266.37