Dept. of Trans. SEMI-FINAL Serial No. Contract No. 03-262-14-35 07-183904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-101-0.1/0.8 Federal Project: ACNH-Q101(11) Progress payment No. 07 Payment period ending: 06-30-03 J MC LOUGHLIN ENGINEERING CO INC 10722 ARROW ROUTE STE 716 RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 374,226.84 0.00 2.a. Extra Work 79,142.31 79,142.31 b. Adjustment Comp. -7,512.13 -7,512.13 3. Materials on Hand 4. Earned Subject to Retention 445,857.02 71,630.18 5. Mobilization 60,000.00 0.00 6. Total Work Completed 505,857.02 7. Deductions 0.00 25,000.00 8. a.Contract Retentions -17,529.34 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 17,529.34 0.00 9. Total pay to Contractor 505,857.02 96,630.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 96,630.18