Dept. of Trans. PROGRESS Serial No. Contract No. 11-265-10-40 07-184104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 11% 07-LA-5-15.8/16.9 Federal Project: ACHS-052(948) IMG-052(948) Progress payment No. 05 Payment period ending: 09-20-11 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 586,422.50 315,349.20 2.a. Extra Work 25,804.20 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 612,226.70 315,349.20 5. Mobilization 33,750.00 11,250.00 6. Total Work Completed 645,976.70 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 645,976.70 326,599.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 326,599.20