Dept. of Trans. PROGRESS Serial No. Contract No. 07-115-09-08 07-184904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 30% 97% 07-LA-23-0.0/8.9 Federal Project: NONE Progress payment No. 07 Payment period ending: 04-20-07 SULLY MILLER CONTRACTING COMPANY 1100 E ORANGETHORPE AVE #200 ANAHEIM CA 92801 Escrow No. 02248 Total Estimate This Estimate 1. Contract Itms Without Mobil. 723,446.50 94,983.50 2.a. Extra Work 47,651.85 38,903.71 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 771,098.35 133,887.21 5. Mobilization 114,000.00 0.00 6. Total Work Completed 885,098.35 7. Deductions -9,000.00 -4,500.00 8. a.Contract Retentions -54,945.21 0.00 b. Unsatisfactory Prog. 0.00 7,044.70 c. Reduction after 95% Comp. 9. Total pay to Contractor 821,153.14 136,431.91 10. Reduction Amt to Escrow 11. Payment to Escrow 54,940.00 12. Net Pymt. this Estimate 136,431.91