Dept. of Trans. PROGRESS Serial No. Contract No. 07-268-09-31 07-184904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 100% 07-LA-23-0.0/8.9 Federal Project: NONE Progress payment No. 11 Payment period ending: 09-20-07 SULLY MILLER CONTRACTING COMPANY 1100 E ORANGETHORPE AVE #200 ANAHEIM CA 92801 Escrow No. 02248 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,656,201.28 166,084.78 2.a. Extra Work 57,393.75 0.00 b. Adjustment Comp. -8,495.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,705,099.18 166,084.78 5. Mobilization 120,000.00 0.00 6. Total Work Completed 2,825,099.18 7. Deductions -9,000.00 0.00 8. a.Contract Retentions -135,254.96 -8,304.24 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,680,844.22 157,780.54 10. Reduction Amt to Escrow 11. Payment to Escrow 135,250.00 12. Net Pymt. this Estimate 157,780.54