Dept. of Trans. PROGRESS Serial No. Contract No. 07-297-08-26 07-184904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 54% 07-LA-23-0.0/8.9 Federal Project: NONE Progress payment No. 12 Payment period ending: 10-20-07 SULLY MILLER CONTRACTING COMPANY 1100 E ORANGETHORPE AVE #200 ANAHEIM CA 92801 Escrow No. 02248 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,689,561.28 33,360.00 2.a. Extra Work 57,393.75 0.00 b. Adjustment Comp. -8,495.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,738,459.18 33,360.00 5. Mobilization 120,000.00 0.00 6. Total Work Completed 2,858,459.18 7. Deductions -9,000.00 0.00 8. a.Contract Retentions -136,922.96 -1,668.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,712,536.22 31,692.00 10. Reduction Amt to Escrow 11. Payment to Escrow 136,920.00 12. Net Pymt. this Estimate 31,692.00