Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-088-09-39 07-184904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-23-0.0/8.9 Federal Project: NONE Progress payment No. 14 Payment period ending: 11-14-07 SULLY MILLER CONTRACTING COMPANY 1100 E ORANGETHORPE AVE #200 ANAHEIM CA 92801 Escrow No. 02248 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,689,561.28 0.00 2.a. Extra Work 150,242.03 64,875.85 b. Adjustment Comp. -9,646.05 -1,150.20 3. Materials on Hand 4. Earned Subject to Retention 2,830,157.26 63,725.65 5. Mobilization 120,000.00 0.00 6. Total Work Completed 2,950,157.26 7. Deductions 8. a.Contract Retentions -136,922.96 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 136,922.96 0.00 9. Total pay to Contractor 2,950,157.26 63,725.65 10. Reduction Amt to Escrow -136,920.00 0.00 11. Payment to Escrow 136,920.00 12. Net Pymt. this Estimate 63,725.65