Dept. of Trans. PROGRESS Serial No. Contract No. 03-330-08-44 07-187204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 40% 07-LA-126-R5.7/R6.4 Federal Project: ACNH-P126(47) ACNH-005-3(38) I-005-3(38) Progress payment No. 09 Payment period ending: 11-20-03 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02061 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,600,829.19 616,708.71 2.a. Extra Work 174,400.54 2,883.89 b. Adjustment Comp. 4,984.16 0.00 3. Materials on Hand 146,575.00 -51,955.00 4. Earned Subject to Retention 5,926,788.89 567,637.60 5. Mobilization 484,500.00 0.00 6. Total Work Completed 6,264,713.89 7. Deductions -62,000.00 -10,000.00 8. a.Contract Retentions -334,400.05 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,014,888.84 557,637.60 10. Reduction Amt to Escrow 11. Payment to Escrow 334,400.00 12. Net Pymt. this Estimate 557,637.60