Dept. of Trans. PROGRESS Serial No. Contract No. 04-056-09-54 07-187204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 52% 07-LA-126-R5.7/R6.4 Federal Project: ACNH-P126(47) ACNH-005-3(38) I-005-3(38) Progress payment No. 12 Payment period ending: 02-20-04 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02061 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,567,653.85 731,306.28 2.a. Extra Work 252,949.51 28,362.05 b. Adjustment Comp. 5,778.76 -2,270.80 3. Materials on Hand 274,617.00 144,237.00 4. Earned Subject to Retention 8,100,999.12 901,634.53 5. Mobilization 484,500.00 0.00 6. Total Work Completed 8,310,882.12 7. Deductions -72,000.00 0.00 8. a.Contract Retentions -405,049.96 -45,081.73 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,108,449.16 856,552.80 10. Reduction Amt to Escrow 11. Payment to Escrow 405,040.00 12. Net Pymt. this Estimate 856,552.80