Dept. of Trans. PROGRESS Serial No. Contract No. 04-238-13-02 07-187204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 80% 07-LA-126-R5.7/R6.4 Federal Project: ACNH-P126(47) ACNH-005-3(38) I-005-3(38) Progress payment No. 18 Payment period ending: 08-20-04 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02061 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,240,739.97 772,883.89 2.a. Extra Work 445,050.45 20,062.52 b. Adjustment Comp. 67,789.10 0.00 3. Materials on Hand 223,654.67 -107,883.43 4. Earned Subject to Retention 11,977,234.19 685,062.98 5. Mobilization 510,000.00 0.00 6. Total Work Completed 12,263,579.52 7. Deductions -72,000.00 0.00 8. a.Contract Retentions -598,861.71 -34,253.15 b. Unsatisfactory Prog. -34,253.15 -34,253.15 c. Reduction after 95% Comp. 9. Total pay to Contractor 11,782,119.33 616,556.68 10. Reduction Amt to Escrow 11. Payment to Escrow 598,860.00 12. Net Pymt. this Estimate 616,556.68