Dept. of Trans. PROGRESS Serial No. Contract No. 04-266-10-14 07-187204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 84% 07-LA-126-R5.7/R6.4 Federal Project: ACNH-P126(47) ACNH-005-3(38) I-005-3(38) Progress payment No. 19 Payment period ending: 09-20-04 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02061 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,614,106.71 373,366.74 2.a. Extra Work 476,409.99 31,359.54 b. Adjustment Comp. 28,923.39 -38,865.71 3. Materials on Hand 192,282.42 -31,372.25 4. Earned Subject to Retention 12,311,722.51 334,488.32 5. Mobilization 510,000.00 0.00 6. Total Work Completed 12,629,440.09 7. Deductions -82,000.00 -10,000.00 8. a.Contract Retentions -615,586.13 -16,724.42 b. Unsatisfactory Prog. -50,977.56 -16,724.41 c. Reduction after 95% Comp. 9. Total pay to Contractor 12,073,158.82 291,039.49 10. Reduction Amt to Escrow 11. Payment to Escrow 615,580.00 12. Net Pymt. this Estimate 291,039.49