Dept. of Trans. PROGRESS Serial No. Contract No. 04-334-15-58 07-187204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 92% 07-LA-126-R5.7/R6.4 Federal Project: ACNH-P126(47) ACNH-005-3(38) I-005-3(38) Progress payment No. 21 Payment period ending: 11-20-04 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02061 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,019,327.38 38,522.20 2.a. Extra Work 701,865.81 144,849.42 b. Adjustment Comp. 1,979.86 -33,681.49 3. Materials on Hand 211,309.52 64,927.10 4. Earned Subject to Retention 12,934,482.57 214,617.23 5. Mobilization 510,000.00 0.00 6. Total Work Completed 13,233,173.05 7. Deductions -56,180.00 30,000.00 8. a.Contract Retentions -646,724.13 -10,730.86 b. Unsatisfactory Prog. 0.00 71,384.70 c. Reduction after 95% Comp. 9. Total pay to Contractor 12,741,578.44 305,271.07 10. Reduction Amt to Escrow 11. Payment to Escrow 646,720.00 12. Net Pymt. this Estimate 305,271.07