Dept. of Trans. PROGRESS Serial No. Contract No. 05-081-15-09 07-187204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 100% 07-LA-126-R5.7/R6.4 Federal Project: ACNH-P126(47) ACNH-005-3(38) I-005-3(38) Progress payment No. 25 Payment period ending: 03-20-05 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02061 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,489,904.51 181,491.04 2.a. Extra Work 873,475.10 38,555.97 b. Adjustment Comp. 6,386.75 0.00 3. Materials on Hand 507,645.06 246,912.60 4. Earned Subject to Retention 14,877,411.42 466,959.61 5. Mobilization 510,000.00 0.00 6. Total Work Completed 14,879,766.36 7. Deductions -36,180.00 -10,000.00 8. a.Contract Retentions -743,870.57 -23,347.98 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,607,360.85 433,611.63 10. Reduction Amt to Escrow 11. Payment to Escrow 743,870.00 12. Net Pymt. this Estimate 433,611.63