Dept. of Trans. PROGRESS Serial No. Contract No. 05-172-10-20 07-187204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 100% 07-LA-126-R5.7/R6.4 Federal Project: ACNH-P126(47) ACNH-005-3(38) I-005-3(38) Progress payment No. 28 Payment period ending: 06-20-05 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 02061 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,784,925.34 272,471.96 2.a. Extra Work 971,090.20 7,770.37 b. Adjustment Comp. 6,386.75 0.00 3. Materials on Hand 224,473.06 -46,387.00 4. Earned Subject to Retention 15,986,875.35 233,855.33 5. Mobilization 510,000.00 0.00 6. Total Work Completed 16,272,402.29 7. Deductions -42,130.00 -4,800.00 8. a.Contract Retentions -799,343.77 -11,692.77 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,655,401.58 217,362.56 10. Reduction Amt to Escrow 11. Payment to Escrow 799,340.00 12. Net Pymt. this Estimate 217,362.56