Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-228-14-01 07-187504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-5-15.2/15.3 Federal Project: ACNH-Q101(70) ACIM-005-2(914) Progress payment No. 21 Payment period ending: 07-18-06 A P ENGINEERING CORPORATION 1271 COLUMBIA AVENUE SUITE 10 RIVERSIDE CA 92507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 900,313.50 62,975.00 2.a. Extra Work 31,255.90 2,990.00 b. Adjustment Comp. 10,500.00 5,000.00 3. Materials on Hand 4. Earned Subject to Retention 942,069.40 70,965.00 5. Mobilization 64,000.00 0.00 6. Total Work Completed 1,006,069.40 7. Deductions -51,509.57 -7,870.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 954,559.83 63,095.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 63,095.00