Dept. of Trans. PROGRESS Serial No. Contract No. 06-082-08-15 07-188204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 134% 07-LA-110-18.2/19.6 Federal Project: ACIM-110-1(779) Progress payment No. 04 Payment period ending: 03-20-06 ODONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 110,741.00 50,699.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 46,046.00 -5,313.30 4. Earned Subject to Retention 156,787.00 45,385.70 5. Mobilization 61,750.00 13,000.00 6. Total Work Completed 172,491.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 218,537.00 58,385.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,385.70