Dept. of Trans. PROGRESS Serial No. Contract No. 08-023-11-52 07-193104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 50% 07-LA-5-16.9/28.7 Federal Project: ACIM-005-3(64) Progress payment No. 25 Payment period ending: 01-20-08 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,931,495.03 300,937.56 2.a. Extra Work 152,132.01 19,537.54 b. Adjustment Comp. -36,211.25 -3,503.45 3. Materials on Hand 407,478.91 -2,323.00 4. Earned Subject to Retention 21,454,894.70 314,648.65 5. Mobilization 4,208,500.00 0.00 6. Total Work Completed 25,255,915.79 7. Deductions -41,695.52 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,621,699.18 314,648.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 314,648.65