Dept. of Trans. PROGRESS Serial No. Contract No. 09-112-15-25 07-193104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 81% 07-LA-5-16.9/28.7 Federal Project: ACIM-005-3(64) Progress payment No. 40 Payment period ending: 04-20-09 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS, CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,490,895.54 1,076,176.93 2.a. Extra Work 403,495.74 12,429.09 b. Adjustment Comp. 36,646.71 -4,752.23 3. Materials on Hand 210,096.32 -2,307.00 4. Earned Subject to Retention 34,141,134.31 1,081,546.79 5. Mobilization 4,430,000.00 0.00 6. Total Work Completed 38,361,037.99 7. Deductions -53,283.02 -10,400.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 38,517,851.29 1,071,146.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,071,146.79