Dept. of Trans. PROGRESS Serial No. Contract No. 04-173-15-06 07-194904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 44% 07-LA-47-3.6/4.3 Federal Project: ACNH-P047(5) Progress payment No. 04 Payment period ending: 06-20-04 WILLIAM P YOUNG CONSTRUCTION INC 4055 NELSON AVENUE CONCORD CA 94520 Escrow No. 02161 Total Estimate This Estimate 1. Contract Itms Without Mobil. 162,387.10 46,584.00 2.a. Extra Work 19,396.92 0.00 b. Adjustment Comp. 3. Materials on Hand 110,690.05 0.00 4. Earned Subject to Retention 292,474.07 46,584.00 5. Mobilization 195,000.00 65,000.00 6. Total Work Completed 376,784.02 7. Deductions -9,058.40 -6,308.40 8. a.Contract Retentions -29,247.41 -4,658.40 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 449,168.26 100,617.20 10. Reduction Amt to Escrow 11. Payment to Escrow 29,240.00 12. Net Pymt. this Estimate 100,617.20