Dept. of Trans. PROGRESS Serial No. Contract No. 04-238-13-02 07-194904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 67% 07-LA-47-3.6/4.3 Federal Project: ACNH-P047(5) Progress payment No. 06 Payment period ending: 08-20-04 WILLIAM P YOUNG CONSTRUCTION INC 4055 NELSON AVENUE CONCORD CA 94520 Escrow No. 02161 Total Estimate This Estimate 1. Contract Itms Without Mobil. 522,678.84 210,941.54 2.a. Extra Work 34,996.92 15,600.00 b. Adjustment Comp. 3. Materials on Hand 75,711.13 -21,094.10 4. Earned Subject to Retention 633,386.89 205,447.44 5. Mobilization 247,000.00 52,000.00 6. Total Work Completed 804,675.76 7. Deductions -4,400.00 0.00 8. a.Contract Retentions -52,896.48 -10,102.53 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 823,090.41 247,344.91 10. Reduction Amt to Escrow 11. Payment to Escrow 52,890.00 12. Net Pymt. this Estimate 247,344.91