Dept. of Trans. PROGRESS Serial No. Contract No. 14-328-10-11 07-1952U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 28% 07-VEN-101-R0.1/R4.5 Federal Project: CNHP-X037(165) Progress payment No. 12 Payment period ending: 11-20-14 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,642,023.04 896,866.39 2.a. Extra Work 250,892.56 50,596.97 b. Adjustment Comp. 3. Materials on Hand 402,513.31 -50,000.00 4. Earned Subject to Retention 6,295,428.91 897,463.36 5. Mobilization 1,582,149.00 0.00 6. Total Work Completed 7,475,064.60 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,877,577.91 897,463.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 897,463.36