Dept. of Trans. PROGRESS Serial No. Contract No. 15-173-14-14 07-1952U4 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 46% Location: Federal Project: 07-VEN-101-R0.1/R4.5 CNHP-X037(165) Progress payment No. 019 Payment period ending: 06-20-15 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,254,304.20 1,641,160.43 2. a. Extra Work 591,211.63 14,944.22 b. Adustment Comp. 264,500.00 69,907.35 3. Materials on Hand 95,364.18 -10,174.00 4. Earned Subject to Retention 13,205,380.01 1,715,838.00 5. Mobilization 1,665,420.00 83,271.00 6. Total Work Completed 14,775,435.83 7. Deductions -1,420.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,869,380.01 1,799,109.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,799,109.00