Dept. of Trans. PROGRESS Serial No. Contract No. 16-054-18-05 07-1952U4 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 65% Location: Federal Project: 07-VEN-101-R0.1/R4.5 CNHP-X037(165) Progress payment No. 028 Payment period ending: 02-20-16 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,651,288.19 358,856.70 2. a. Extra Work 1,677,679.99 18,909.37 b. Adustment Comp. 352,884.08 0.00 3. Materials on Hand 194,758.00 0.00 4. Earned Subject to Retention 19,876,610.26 377,766.07 5. Mobilization 1,665,420.00 0.00 6. Total Work Completed 21,347,272.26 7. Deductions -31,420.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,510,610.26 367,766.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 367,766.07