Dept. of Trans. PROGRESS Serial No. Contract No. 16-083-15-29 07-1952U4 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 65% Location: Federal Project: 07-VEN-101-R0.1/R4.5 CNHP-X037(165) Progress payment No. 029 Payment period ending: 03-20-16 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,638,922.87 987,634.68 2. a. Extra Work 1,694,703.02 17,023.03 b. Adustment Comp. 352,884.08 0.00 3. Materials on Hand 6,651.00 -188,107.00 4. Earned Subject to Retention 20,693,160.97 816,550.71 5. Mobilization 1,665,420.00 0.00 6. Total Work Completed 22,351,929.97 7. Deductions -11,420.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,347,160.97 836,550.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 836,550.71