Dept. of Trans. PROGRESS Serial No. Contract No. 00-357-15-10 07-199704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 8% 07-LA-134-0.0/R13.3 Federal Project: ACNH-P134(27) Progress payment No. 02 Payment period ending: 12-20-00 WEST COAST BRIDGE INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 144,908.50 139,908.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 144,908.50 139,908.50 5. Mobilization 6. Total Work Completed 144,908.50 7. Deductions 8. a.Contract Retentions -14,490.85 -13,990.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 130,417.65 125,917.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 125,917.65