Dept. of Trans. PROGRESS Serial No. Contract No. 01-206-06-55 07-199704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 57% 07-LA-134-0.0/R13.3 Federal Project: ACNH-P134(27) Progress payment No. 09 Payment period ending: 07-20-01 WEST COAST BRIDGE INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 01690 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,938,001.90 226,561.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,938,001.90 226,561.00 5. Mobilization 390,000.00 19,500.00 6. Total Work Completed 3,328,001.90 7. Deductions -8,400.00 0.00 8. a.Contract Retentions -146,900.10 -11,328.05 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,172,701.80 234,732.95 10. Reduction Amt to Escrow 11. Payment to Escrow 146,900.00 12. Net Pymt. this Estimate 234,732.95