Dept. of Trans. PROGRESS Serial No. Contract No. 06-234-15-02 07-1P1504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 68% 07-LA-5-85.6/86.5 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-06 ALLIED PAVING COMPANY 1234 NORTH BLUE GUM STREET ANAHEIM CA 928062411 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 240,791.08 240,791.08 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 240,791.08 240,791.08 5. Mobilization 8,500.00 8,500.00 6. Total Work Completed 249,291.08 7. Deductions -1,125.00 -1,125.00 8. a.Contract Retentions -12,039.55 -12,039.55 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 236,126.53 236,126.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 236,126.53