Dept. of Trans. PROGRESS Serial No. Contract No. 07-115-08-41 07-1P5704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 58% 07-VEN-1-4.0/4.7 Federal Project: NONE Progress payment No. 03 Payment period ending: 04-20-07 RSB GROUP INC 22865 LAKE FOREST DRIVE STE 2 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 134,150.00 0.00 2.a. Extra Work 66,473.26 66,473.26 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 200,623.26 66,473.26 5. Mobilization 38,450.00 0.00 6. Total Work Completed 239,073.26 7. Deductions -18,990.00 0.00 8. a.Contract Retentions -10,031.16 -3,323.66 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 210,052.10 63,149.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 63,149.60