Dept. of Trans. PROGRESS Serial No. Contract No. 08-143-10-58 07-1P6804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 70% 07-VEN-126-28.3/28.3 Federal Project: NONE Progress payment No. 04 Payment period ending: 05-20-08 FREEWAY ELECTRIC P O BOX 7745 RIVERSIDE CA 925137745 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 91,703.66 27,103.66 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -18,713.17 4. Earned Subject to Retention 91,703.66 8,390.49 5. Mobilization 5,015.68 0.00 6. Total Work Completed 96,719.34 7. Deductions -100.00 0.00 8. a.Contract Retentions -4,585.18 -419.52 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 92,034.16 7,970.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,970.97