Dept. of Trans. PROGRESS Serial No. Contract No. 07-143-08-04 07-1P7504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 70% 07-LA-105-R1.5/R1.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 05-20-07 FLEMING ENVIRONMENTAL INCORPORATED 6130 VALLEY VIEW STREET BUENA PARK CA 906201030 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 81,941.00 29,548.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 81,941.00 29,548.00 5. Mobilization 24,301.00 5,116.00 6. Total Work Completed 106,242.00 7. Deductions 8. a.Contract Retentions -5,469.60 -230.30 b. Unsatisfactory Prog. -1,477.40 -1,477.40 c. Reduction after 95% Comp. 9. Total pay to Contractor 99,295.00 32,956.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,956.30