Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-120-14-50 07-1P8004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-5758 Federal Project: NONE Progress payment No. 02 Payment period ending: 04-11-07 CROWN FENCE CO 12118 BLOOMFIELD AVE SANTA FE SPRINGS CA 90670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 184,484.15 180,995.15 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 184,484.15 180,995.15 5. Mobilization 6. Total Work Completed 184,484.15 7. Deductions 8. a.Contract Retentions -348.90 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 348.90 348.90 9. Total pay to Contractor 184,484.15 181,344.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 181,344.05