Dept. of Trans. PROGRESS Serial No. Contract No. 13-164-13-21 07-1W0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 55% 07-LA-210-R9.0/R48.1 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-20-13 US SPECIALTY INSURANCE COMPANY 601 S. FIGUEROA ST., STE 1600 LOS ANGELES, CA 90017 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 451,367.71 177,398.71 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 165,305.38 165,305.38 4. Earned Subject to Retention 616,673.09 342,704.09 5. Mobilization 100,800.00 5,040.00 6. Total Work Completed 552,167.71 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 717,473.09 347,744.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 347,744.09